Multi-criteria Decision Analysis: To select team members based on a no. of factors: availability, cost, experience, ability, knowledge, skills, attitude, etc.
2 of the Perform Quality Assurance Tools & Techniques are
-Quality Audit - "Quality Audits are reviews of your project by your company. They figure out whether or not you are following the company's process."
-Process Analysis - "Process Analysis is when you look at your process to find out how to make it better. You use your Process Improvement plan to do this one."
halo effect: a cognitive bias (if he is good at one thing, he will be good at everything)
recognition should focus on win-win reward for the team (NOT competitive-based)
# Team Building Activity
Milestone parties
Outdoor activities, eg. work trips, basketball match, soccer match, etc
Creating WBS
Planning the project by getting everyone involved in some way.
Co-location
A reward and recognition System
Quality Function Deployment (QFD) - A type of facilitated workshop that aims in determining the critical features to develop a new product.It begins by collecting the needs of the customer (also known as Voice of the Customers). Once the VOCs are collected, they are then sorted and prioritized objectively so that the goals can be set to achieve them.
- The 8/80 Rule states that the work package should not equate to less than eight hours of labor to create and no more than 80 hours of labor to create.
- Sunk costs are costs that are already incurred in the project. These costs should not be taken into account during project evaluation.
- EMV = (Probability) x (Impact)
2 of the Perform Quality Assurance Tools & Techniques are
-Quality Audit - "Quality Audits are reviews of your project by your company. They figure out whether or not you are following the company's process."
-Process Analysis - "Process Analysis is when you look at your process to find out how to make it better. You use your Process Improvement plan to do this one."
halo effect: a cognitive bias (if he is good at one thing, he will be good at everything)
recognition should focus on win-win reward for the team (NOT competitive-based)
# Team Building Activity
Milestone parties
Outdoor activities, eg. work trips, basketball match, soccer match, etc
Creating WBS
Planning the project by getting everyone involved in some way.
Co-location
A reward and recognition System
Quality Function Deployment (QFD) - A type of facilitated workshop that aims in determining the critical features to develop a new product.It begins by collecting the needs of the customer (also known as Voice of the Customers). Once the VOCs are collected, they are then sorted and prioritized objectively so that the goals can be set to achieve them.
- The 8/80 Rule states that the work package should not equate to less than eight hours of labor to create and no more than 80 hours of labor to create.
- Sunk costs are costs that are already incurred in the project. These costs should not be taken into account during project evaluation.
- EMV = (Probability) x (Impact)